    • MacArthur Heights Views

      September 09, 2019

      One of our current projects is this impressive West Coast style home in MacArthur Heights. The home faces the lake looking west, and the views are absolutely mesmerizing.

      Currently, we're at lockup stage and are preparing to move into the finishing stages. Recent progress includes installation of windows and construction door sets, strapping installed under the deck in preparation for soffits, installation of slab SM insulation and finishing of basement concrete floor, framing of lower floor interior walls and main floor stairs, Duradek installation, and completion of waterproof roofing membrane in preparation for custom metal roofing installation.

      Siding and soffit selections are confirmed with a mix of HardiePlank, HardiePanel, and aluminum and Lux metal soffits with select wood beam accents.  Rough-ins are underway for HVAC and plumbing. Electrical rough-ins will begin shortly.

      Critical finishing decisions have been made by our clients, including fireplaces, flooring, cabinets, lighting, countertops, finishing trims, interior doors and hardware, overhead garage door, and paint choices.

      The septic tank and field have installed, and the garage floor has been prepped with rebar and 6 mil vapor barrier (above and beyond BC Building Code requirements) in preparation for slab install and finishing.

      The entire project is on-time for February completion. Stay tuned for more details.