    • Ross Creek Waterfront Framing

      July 02, 2017
      Weather is cooperating nicely for the framing of this Ross Creek waterfront residence.

      Trusses are installing along with stained timber frame accents on the front of the home with the rear soon to follow. Roofers are scheduled and 50 year asphalt shingles are on order.

      Custom made wood windows are in production, a long with matching factory stained trims for that perfect match.

      Landscapers are currently reviewing design plans which include low maintenance planting zones and natural rock walls.

      Custom cabinetry with built-in plan designs are finalizing to be followed with sub-floor layouts to help support plumbers, heating and ventilation and electrical crews with their layouts.

      Challenge now is finding 6 weeks in the schedule lost due to inclement weather and structural engineering upgrades. It's busy out there!