    • Scotch Creek Waterfront Framing

      April 21, 2017
      Although mother nature's sense of humor this Spring has been challenging, with higher than normal amounts of wind and rain, framing continues to progress nicely on this Scotch Creek waterfront home.

      Engineered structural steel sheer walls are now in place, having been assembled on site and erected by crane.

      Basement and crawlspace concrete has been placed and finished.

      Stained timber frame product is arriving to match construction schedules to ensure minimal weathering and potential for damage during construction.

      Temporary stairs from the main to upper floor are in place to enable easy access for trades and home owners while CAD drawings are finalizing for a future curved and open staircase.

      99% of the finishing selections have been confirmed, a testament to the commitment and focus of both the home owners, Bill & Ina, as well as interior designer, Kevin Gray. Job well done!

      Heating and Ventilation systems are finalized, including multi-zoned radiant floor heat for both floors, Lennox zoned high velocity heating and cooling, heat recovery ventilation, Panasonic low sone bath fans and evaporative steam humidification.

      Plumbing systems include Bosch gas boiler controlled domestic and radiant water, whole house reverse osmosis, level entry showers and select cast iron sound control piping.

      Roof trusses are in production and scheduled for arrival toward month's end.

      Enviroslate roofing with ridge venting and engineered snow stops are ordered and scheduled for install.