      April 07, 2017
      Finishing work is well underway with custom window liner, baseboard and window casing installation. Painters are standing by to spray finish all wall finishing trims.

      Exterior siding is complete and subject to a quality control inspection and final calking and touch-ups.

      Cabinets, flooring and custom stair railings are scheduled and installing upon completion of wood ceiling finishing.

      Upper yard concrete retaining walls are under construction with an anticipated pour this week. Septic field pipe and upper yard installation is scheduled upon form stripping and water-proofing membrane installation. Driveways have been prepared for future finishing.

      Ceiling wood materials are currently being sprayed in preparation for next week's installation.