    • North Shore Foundation Completed

      March 30, 2017
      Spring has finally sprung, resulting in perfect foundation concrete pour temperatures.

      Foundation forms are stripped, inspected and sealed. Perimeter drains are in place and foundation backfill is complete. Concrete is in perfect condition with no voids or cracks.

      Crawlspace radon drain rock and piping is in place and garage is back-filled with drain rock for best compaction. Vapor barrier is in place and sealed to the foundation walls for next week's concrete pour.

      Although geotechnical soils analysis revealed positive soils drainage, conversations with neighbors revealed evidence of seasonal high water tables from Ross Creek. Due diligence necessitated the installation of a crawlspace sump pump.

      Floor joists are ordered.