    • Highlands Progress

      February 24, 2017
      Finishing stages are progressing nicely on this Shuswap Lake Estates view home. The team has worked well to gain back scheduling delays that resulted from our drywall boarder's broken toe. Always something interesting!

      Cabinets are installed, as are custom stained stair railings and spindles. A custom fireplace mantle is being finished and stained.

      Bathroom floor tile is complete and just waiting for finish grout. Hardwood starts this week and carpet is being held off until sub-trade traffic becomes manageable.

      The majority of the siding is now complete and just waiting for warmer weather for final calking and touch-ups. Masonry stone is ordered and will be arriving along with warmer weather.

      The crews are waiting patiently for Spring, the removal of road bans and an opportunity to put the finishing touches on Brian and Sherry's concrete entry stairs and driveway.